Projects

We currently operate seven production/work-over rigs, 10 circulating pumps, a twenty-one well lease in Los Angeles, and 8 wells in Signal Hill/Long Beach.

AllenCo Long Beach California

Port of Long Beach

In February 2003, AllenCo was awarded a contract to abandon twenty-nine oil wells in the Port of Long Beach and extract all surface pipes from 130 ft. The casing sizes were 18” and 30”. All the wells were on the channel and were abandoned by cutting surface casing, fishing, cementing, and vibrating out surface pipe. Five rigs were used. Long Beach, Harbor Dept. No. HD-S2191.

Whiting Turner

In 2004, Del Amo Fashion Mall contracted five oil well abandonments. All wells required cementing, cutting, and pulling casing. Two rigs were used.

Warren E&P

AllenCo provides ongoing rigs for production and work-overs. Work consists of cementing, well control, fishing, and acid stimulation. One to two rigs used constantly.